Book the shower screen measure too early and the sizes are wrong; too late and the job stalls. Where it fits in your program and what to have ready.
The shower screen is one of the last things to go into a bathroom, which is exactly why it gets squeezed. Book the measure too early and the sizes are wrong once the tiler finishes. Book it too late and the bathroom sits waiting on glass while the rest of the house is ready for handover. Getting the timing right is mostly about knowing what has to be finished first.
Here is how we suggest slotting the shower screen measure into your program, what tends to hold it up, and what to send your supplier so the order goes through without back and forth.
Why the measure has to wait
A custom screen is made to the finished surfaces of the shower recess, not the frame or the sheeting. Every millimetre of tile, adhesive, trim and grout changes the final size. If the measure happens before tiling is complete, the glass is being made to a space that does not exist yet.
With frameless screens in particular there is no frame to take up a small error. A panel made to pre-tiling dimensions can leave gaps you cannot hide or simply not fit.
Where the measure sits in the sequence
Every builder runs their program a little differently, but for wet areas the order of trades is fairly consistent. In broad terms:
- Framing and backing: allow for noggings or suitable backing where screen hinges, clamps or channels will fix, especially for frameless designs.
- Rough-in plumbing and drainage: including the position of any linear or strip drain on a hobless shower.
- Wall sheeting and floor preparation: including set-downs and screeds that create the falls to the waste.
- Waterproofing: membrane applied and cured to the manufacturer’s instructions, and inspected or signed off as your process and jurisdiction require.
- Tiling: walls and floor complete, including trims, niches and feature tiles.
- Grouting and silicone: finished, with internal corners and junctions sealed.
- Tapware and fixtures: fitted, or at least their final positions confirmed.
- Shower screen measure: once the above is done and the recess is in its final state.
The practical trigger is simple: book the measure when the tiler has finished and cleaned up in that bathroom, not when they start.
Hobless showers and linear drains
Hobless showers look great but they put more pressure on the screen detail. The floor falls toward the drain, and the screen often sits across or beside that fall. A few things to lock down before the measure:
- Confirm the drain location and which side of the screen it sits on.
- Check that the falls are formed as designed so water heads to the waste and not out into the room.
- Decide whether the screen will sit in a channel, on a threshold or direct on the tile, since this affects the glass height and how the base is sealed.
- Keep in mind that the screen alone does not make a wet area compliant. Falls, waterproofing and the shower area layout all need to work together.
Waterproofing of domestic wet areas is covered by AS 3740 and the National Construction Code. Requirements vary with the shower design, so confirm the detail for your project with your certifier or waterproofing contractor.
Common causes of delay
Most shower screen hold-ups we hear about come back to a handful of issues:
- Tiling not finished: a missing row of tiles, a trim yet to go on or a niche not completed.
- Selections not made: the client has not chosen glass type, hardware finish or door configuration.
- Plans and site do not match: the recess was changed on site and the drawings were never updated.
- Out-of-plumb walls discovered late: a lean that nobody flagged until the glass had to fit it.
- Access issues: no one on site, locked gates, or a bathroom full of other trades’ gear.
- Fixing positions unclear: no record of where backing was installed for frameless hardware.
None of these are hard to fix, but each one can cost a revisit and push the job back. A quick check before booking saves most of them.
Site readiness checklist
Run through this before you call the measure:
- Waterproofing complete and cured to the membrane manufacturer’s instructions.
- Wall and floor tiling complete in the shower area, including trims and feature tiles.
- Grout finished and silicone joints complete and cured to the product instructions.
- Falls to the waste formed and checked, especially for hobless showers.
- Tapware, shower rose and any rail positions confirmed.
- Backing locations for hinges and clamps recorded or marked (for frameless).
- Bathroom clear enough to measure accurately, with clean, dry access to the recess.
- Glass type, hardware finish and door opening direction confirmed with the client.
What to send your supplier
The more complete the information up front, the fewer phone calls later. When you book, send:
- Plans: the latest bathroom layout and any elevations showing the shower recess, niches and drain.
- Screen type: framed, semi-frameless or frameless, and the configuration (door, fixed panel, return, walk-in).
- Glass selection: clear, or any other option the client has chosen.
- Hardware finish: the finish chosen for hinges, clamps and channels, ideally matched to the tapware.
- Door swing: which way the door opens and any clearance issues with vanities, toilets or towel rails.
- Site contact: the name and number of the person who will be on site.
- Access details: address, lot number, gate or lockbox codes, parking and any site induction requirements.
- Known issues: out-of-plumb walls, tile changes or anything that differs from the drawings.
For multi-unit jobs, a schedule showing which bathrooms are ready and when the rest are expected helps everyone plan.
Build it into the program early
The easiest way to avoid a shower screen delay is to treat it as a program item from the start, not something you remember at practical completion. Get the screen type and selections locked in when the bathroom is being finalised, plan the backing at frame stage, and pencil the measure in straight after the tiler’s finish date.
Premier Showerscreens & Wardrobes is a trade-only, family-run manufacturer with more than 25 years in the business. Every screen is custom designed and made to order using Australian-standard glass and aluminium products. You can see what we make on our shower screens page, and if the same job needs built-in wardrobes or vanity mirrors, it is worth bundling them into one enquiry.
When you have plans and selections ready, request a trade quote or call the office on (02) 9625 6211, Monday to Friday, 8:30am to 5pm. Regular customers can open a trade account.
FAQs
Can the shower screen be measured before tiling?
It is not recommended. Custom screens are made to the finished tiled surfaces, so measuring before tiling is complete risks glass that does not fit.
Does silicone need to be finished before the measure?
Ideally yes. Grout and silicone should be complete and cured to the product instructions so the recess is in its final state when it is measured.
What slows down a shower screen order most often?
Unfinished tiling, missing glass or hardware selections, and plans that no longer match the site are the most common causes. Send complete information when you book.
Who confirms waterproofing and falls are compliant?
That sits with the builder, waterproofer and certifier. AS 3740 and the NCC set the requirements, so confirm details for your project with your certifier.